Case Study: Large Undercutter Project Completed During Tight Holiday Shut DownScopeThe railroad scheduled a one-week maintenance shut down on their coal line’s main artery to coincide with a holiday closing period for the coal companies. The environment for this artery is particularly prone to mud fouling, and as a result a large segment of the stretch required undercutting. The railroad needed experienced, trained undercutter operators who could provide the high-quality work needed for this critical segment of their rail network and complete it during a tight shut-down period. SolutionHulcher Services responded to this challenge with two excavator / undercutters and two support track hoes. Hulcher operators cleaned out the mud and fouled ballast as the rail gangs followed to drop and tamp new ballast and perform other maintenance-of-way work. Because of the schedule, crews worked days and evenings to complete the undercutting. OutcomeAfter six days Hulcher’s underutters had cleaned the entire stretch of track on this important artery, allowing the railroad to finish its project in the crucial one-week window. The railroad was extremely pleased that this stretch of track, which accounts for a significant portion of their business in the region, was clean, safe and ready for use when the coal companies returned to their operations following the holiday. Click here for more information about Hulcher's undercutter service. |
|
More Case Studies from Hulcher Services:
Engineering Case Studies:- Case Study - Hulcher Clears Fire Damage For Bridge Repair, Performs Driftwood Removal From Bridge Piers
- Case Study - Air Excavation / Vacuum Truck
- Case Study - Railroad Crossing
- Case Study - Grade Stabilization
- Case Study - #20 Switch Change
- Case Study - #15 Switch Change
- Case Study - Pile Driver With Rail
- Case Study - Hulcher Pile Driver, Excavator Support Rail Gang on Bridge Stabilization
- Case Study - Pile Driver, Excavator and Hi-Rail Rotary Dump Truck Stabilize Bank at Bridge Headwall
- Case Study - Excavator and Vibratory Hammer Pile Driver Drive H-Beams for Sound Barrier Wall at Hump Yard
- Case Study - Hulcher Installs Gage Ties for Railroad Tie Gangs
- Case Study - Hulcher Excavator, Wheel Loader and Backhoe Perform Bridge Maintenance
- Project Snapshot - Hulcher Excavator and Crew Perform Load Adjustment of Steel Pipes
- Project Snapshot - Hulcher Forklift and Crew Perform Load Adjustment on Load of Roofing Tiles
- Project Snapshot - Telehandler and Conveyor Perform Load Reduction of Alfalfa Pellets
- Case Study - Hulcher Services Performs Environmental Remediation of Arsenic Contamination at Rail Yard for the Railroad
- Case Study - Hulcher Remediates Pond at Chemical Manufacturing Facility
- Case Study - Emergency Response and Remediation Resolves Major Hazardous Material Spill
- Case Study - Hulcher Services Rehabilitates Containment System for Two Million-Gallon Above Ground Storage Tanks ASTs
- Case Study: Hulcher Services Removes Three Diesel and Lube Oil Above-ground Storage Tanks (ASTs) From Railyard
- Case Study: Hulcher Services Remediates 13,500 Tons of Contaminated Soil at Former Salvage Yard
- Case Study: Hi-Rail Vacuum Truck Cleans Locomotive Service Terminal Work Bay
- Case Study: Hulcher Services Remediates Six 3,000-Gallon Underground Storage Tanks (USTs)
- Case Study - Hulcher Crews Perform Tie Down Work on Military Heavy Equipment
- Project Snapshot - Hulcher Performs Loading and Tie Down of Hopper Cars
- Project Snapshot - Hulcher Performs Loading and Tie Down of Three Damaged Locomotives
- Case Study: Hulcher Services Provides Disaster Response for Railroad's Tornado Damage
- Case Study: Hulcher Provides Disaster Response to Simultaneous Major Flood Events
- Case Study - Demolition
- Case Study - Assortment of Hulcher Equipment Moves 170 Tons Industrial Dredge
- Project Snapshot - Hulcher Dozer Clears Right of Way Vegetation
- Project Snapshot - Grapple Truck and Backhoe Break Down Track Panels
- Case Study - Forklift Ramp and Parking Lot Asphalt
- Case Study - Hulcher Services Grades Five-Acre Lot and Creates Asphalt Pads, Roads and Pathways at Rail Yard
- Project Snapshot - Hulcher Crew Performs Asphalt Work at Rail Yard
- Project Snapshot - Hulcher Clears Vegetation Canopy Over Right-Of-Way
- Case Study - Hulcher Services Demolishes Signals Bridge, Cantilever and Signals Tower for Positive Train Control (PTC) Project


