KEY FACTSPROJECT SUMMARY:Replace #20 switch on a double main in the allotted timeframe TWO-STEP PROCESS:Delivered panels for rail crews to prep, then returned to place switch - reduced track downtime and maximized efficiency SIDEBOOMS:Four sidebooms worked in tandem to place the new switch quickly and precisely SCHEDULE:Old switch removed, site graded and new switch set in under three hours |

Download Printable Version of the #20 Switch Change Case Study (PDF)

Download Core Services Brochure (PDF)

Download Track Maintenance / Maintenance of Way / Engineering Services Brochure (PDF)
SCOPE The railroad needed to change a #20 switch as part of their routine track maintenance program. The switch was on a double main, so the project had to be completed within very tight track windows.
Hulcher mobilized four 583 Caterpillar sidebooms to place the new switch within the challenging schedule limits. The process was handled in two steps. First, Hulcher’s sidebooms moved the panels from two semi trailers and positioned them along the track by the old switch. Over the next few weeks railroad crews welded the panels into one piece and applied the switch box and other “jewelry” that the new switch would need.
Hulcher’s sidebooms returned for the second phase, to remove the old switch and place the new one. Timing was crucial for this phase; the railroad had a three-hour window for them to get the job done. Working in close coordination with the railroad crews, the sidebooms lifted out the old pieces of track, which had been cut into five pieces. With the old track removed, graders and a wheel loader cleaned out the existing ballast to create a clean, smooth surface. The sidebooms then lifted and set the new #20 switch in place.
OUTCOMEThe two-step process for delivering the panels and setting the new switch was an effective solution for the railroad. Hulcher’s crews completed their work within the crucial time window, allowing the railroad to do their maintenance-of-way work with minimal interruption to their operating schedule.
To maximize efficiency and minimize cost to the railroad, Hulcher installed several switches in the same region to reduce the amount of time spent deploying the equipment.
Click here for a printable version of this case study
Return to Track Maintenance / MOW / Engineering Services Case Studies Index — Return to top
Hulcher is Close to You!Click map to view our locations |
Our Services:
Industries Served: |
Connect With HulcherMore About Hulcher |