PROJECT SUMMARY:

Replace #20 switch on a double main in the allotted timeframe

TWO-STEP PROCESS:

Delivered panels for rail crews to prep, then returned to place switch - reduced track downtime and maximized efficiency

SIDEBOOMS:

Four sidebooms worked in tandem to place the new switch quickly and precisely

SCHEDULE:

Old switch removed, site graded and new switch set in under three hours
 

More Information On This Project:

Associated Services:


Equipment Used:

Industries Hulcher Serves:

 

Printable Version of the #20 Switch Change  Case Study
Download Printable Version of the #20 Switch Change Case Study (PDF)

Hulcher Core Services Brochure
Download Core Services Brochure (PDF)

Hulcher Track Maintenance / Maintenance of Way / Engineering Services Brochure
Download Track Maintenance / Maintenance of Way / Engineering Services Brochure (PDF)

 



Hulcher is Close to You!

Click map to view our locations

Our Services:

Industries Served:

Connect With Hulcher

Follow Hulcher  

More About Hulcher