PROJECT SUMMARY:

Remove and replace ties, ballast and rail on 300-foot bridge.

OVERLAPPING SPEEDS THE PROCESS:

The excavator and backhoe removed the old ties as a wheel loader followed to place in the new “tubs”, to compress the work schedule.

RESULTS:

Bridge maintenance completed a half-day early, avoiding any disruptions to the railroad’s traffic schedule.
 

More Information On This Project:

Associated Services:


Equipment Used:

Industries Hulcher Serves:


Printable Version of the Railroad Bridge Maintenance Project Case Study
Download Printable Version of the Railroad Bridge Maintenance Project Case Study (PDF)

Printable Version of the Railroad Backhoe Services Flyer
Download Printable Version of the Railroad Backhoe Services Flyer (PDF)

Hulcher Core Services Brochure
Download Core Services Brochure (PDF)

Hulcher Track Maintenance / Maintenance of Way / Engineering Services Brochure
Download Track Maintenance / Maintenance of Way / Engineering Services Brochure (PDF)

 



 

Hulcher is Close to You!

Click map to view our locations

Our Services:

Industries Served:

Connect With Hulcher

Follow Hulcher  

More About Hulcher